A WBS can be represented as a hierarchical tree diagram
Based on the complexity of the project the hierarchical tree could have more or less levels
Our WBS can also be represented as an outline
1
Project
1.1
Deliverable
1.1.1
Work Package
1.1.1.1
Activity A
1.1.1.2
Activity B
1.1.1.3
Activity C
1.1.2
Work Package
1.1.2.1
Activity D
1.1.2.2
Activity E
1.1.2.3
Activity F
1.1.2.4
Activity G
1.1.3
Work Package
1.1.3.1
Activity H
1.1.3.2
Activity I
1.2
Deliverable
1.2.1
Work Package
1.2.1.1
Activity J
1.2.2
Work Package
1.2.2.1
Activity K
1.2.2.2 Activity L
Both represent the same work breakdown structure.Activities
When defining activities which represent the work that needs to be completed at a granular level within a WBS the order of each activity is the order it should be completed in. The rule of thumb for activities is that they should represent 1 to 2 weeks worth of effort for 1 resource, if they're out side of the 5 to 10 working day range then either they are too granular or too broad.